30 Days or Less
(Assumes CEQA Exemption or Previously Certified Environmental Document)
Tree Removal
Sign Permit
Lot Line Adjustment
Single Family Residence- Alt./Add.
Temporary Use Permit
Home Occupation Permits
Administrative Architecture Review
Temporary Sign Permits |
45 Days or Less (Assumes
CEQA Exemption or Previously Certified Environmental Document)
Large Family Daycares
Administrative Land Use Permits (e.g. outdoor seating, personal
improvement services)
Variances
Master Sign Programs
Architecture Board Review (commercial addition and second story addition
to existing single story home and new single family homes) |
| 90 Days or Less (Assumes
CEQA Exemption Negative Declaration or Previously Certified
Environmental Document) Telecommunication
Facilities
Land Use Permit Applications (e.g. churches, preschools)
Development Plan Applications and Amendments – Retail/Commercial/Office |
120 Days or Less (Assumes
CEQA Exemption, Previously Certified Environmental Document or Negative
Declaration) Large commercial developments |
| 180 Days or
Less (Assumes Negative Declaration)
Mixed-Use Developments
Residential Development Applications
Hillside residential developments
|
180 Days or
More (Assumes EIR or
Complex Negative Declaration) Any project
requiring the preparation of an EIR.
Rezoning
General Plan Amendment
Specific Plan Amendment
Zoning Text Amendment |