SRCC Renovation Project
Posted on 01/29/2020
Reception Modifications

SRCC Renovation Project

The renovation of the San Ramon Community Center began on December 16, 2019 and is scheduled to be completed by April 2020. 

The renovations include the following items: 

  • Miscellaneous plumbing improvements
  • New lighting fixtures installation
  • New acoustical ceiling panels in the Fountain Room
  • Interior painting
  • New tile flooring, base and walls
  • Handrail modifications at the stairway
  • New cabinetry and countertops
  • Installation of wrought iron fencing surrounding the patio at the Plaza Room
  • Installation of a new door system at the main entrance
  • Reception and Transaction area modifications (including a reconfigured counter area)
  • New window coverings and fabric awnings
  • Conversion of the Alcosta Room to much needed office space
  • Installation of new self-serve reservation audio/visual equipment 

Renovations are on schedule and are approximately 25% complete.