Project Name: FY 2009/10 Curb, Gutter and Sidewalk Repairs Project
| Project No.: |
CIP 5450 |
| Date: |
November 24, 2009 - 3:00 PM |
| Project Manager: |
Moustefa Kendroud |
| |
(925) 973-2681 |
| ENGINEER'S ESTIMATE |
TOTAL BID |
| |
$150,000.00 |
| No. |
CONTRACTORS |
TOTAL BID |
| 1 |
RP Engineering Contractors |
$66,025.00 |
| 2 |
EIJ Construction |
$76,163.00 |
| 3 |
Guerra Construction |
$83,615.00 |
| 4 |
JJR Construction, Inc. |
$90,530.00 |
| 5 |
Spencon Construction |
$92,395.00 |
| 6 |
Vanguard Construction |
$100,800.00 |
| 7 |
Weber Tractor Services |
$104,539.00 |
| 8 |
Cinray Construction |
$113,450.00 |
| 9 |
MCS Concrete Inc. |
$117,637.50 |
| 10 |
AJW Construction |
$122,750.00 |
| 11 |
Maxicrete |
$123,850.00 |
| 12 |
Wayne E. Swisher Cement |
$145,300.00 |
| 13 |
Sposeto Engineering, Inc. |
$147,150.00 |
| 14 |
Bruce Carone Grading & Paving, Inc. |
$169,148.00 |
Project Name: FY 2009/10 Pavement Repair Stop Gap Project
| Project No.: |
CIP 5483 |
| Date: |
November 24, 2009 - 2:30 PM |
| Project Manager: |
Peter Phoon |
| |
(925) 973-2675 |
| ENGINEER'S ESTIMATE |
TOTAL BID |
| |
$215,700.00 |
| No. |
CONTRACTORS |
TOTAL BID |
| 1 |
Galedrige Construction |
$165,541.50 |
| 2 |
C.F. Archibald Paving, Inc. |
$189,836.50 |
| 3 |
MCK Services Inc. |
$192,596.50 |
| 4 |
G. Bortolotto and Company, Inc. |
$205,652.40 |
| 5 |
Bruce Carone Grading & Paving, Inc. |
$315,980.00 |
Project Name: Forest Home Farms - Walnut Storage Shed Renovation (Building 14) Project
| Project No.: |
CIP 5502 |
| Date: |
November 24, 2009 - 2:00 PM |
| Project Manager: |
Moustefa Kendroud |
| |
(925) 973-2681 |
| ENGINEER'S ESTIMATE |
TOTAL BID |
| |
$350,000.00 |
| No. |
CONTRACTORS |
TOTAL BID |
| 1 |
Kel-Tec Builders |
$147,144.00 |
| 2 |
Bay Valley Construction, Inc. |
$151,956.00 |
| 3 |
Southland Construction |
$157,080.00 |
| 4 |
Amana Engineering & Construction |
$250,000.00 |
| 5 |
River View Construction |
$258,666.00 |
| 6 |
Solano Construction |
$262,400.00 |
| 7 |
Rodan Builders |
$272,000.00 |
| 8 |
JFC Construction, Inc. |
$295,322.00 |
| 9 |
TPA Construction, Inc. |
$346,000.00 |
Project Name: San Ramon Valley Boulevard Pavement Rehabilitation
(Norris Canyon Road to Bollinger Canyon Road)
Federal Aid Project No. ESPL-5437(022)
| Project No.: |
CIP 5534 |
| Date: |
July 14, 2009 - 2:00 PM |
| Project Manager: |
Peter Phoon |
| |
(925) 973-2675 |
| ENGINEER'S ESTIMATE |
TOTAL BID |
| |
$1,496,595.00 |
| No. |
CONTRACTORS |
TOTAL BID |
| 1 |
MCK Services Inc. |
$961,479.35 |
| 2 |
Top Grade Construction, Inc. |
$986,690.35 |
| 3 |
Bay Cities Paving & Grading, Inc. |
$995,003.45 |
| 4 |
Pavex Construction |
$1,047,908.00 |
| 5 |
Granite Construction Co. |
$1,154,758.50 |
| 6 |
C.F. Archibald Paving, Inc. |
$1,224,115.00 |
| 7 |
O'Grady Paving, Inc. |
$1,335,360.00 |
| 8 |
G. Bortolotto and Company, Inc. |
$1,382,947.11 |
Project Name: FY 2008/09 Pavement Management Project
| Project No.: |
CIP 5409 |
| Date: |
May 12, 2009 - 2:00 PM |
| Project Manager: |
Peter Phoon |
| |
(925) 973-2675 |
| ENGINEER'S ESTIMATE |
TOTAL BID |
| |
$2,259,056.50 |
| No. |
CONTRACTORS |
TOTAL BID |
| 1 |
MCK Services Inc. |
$1,739,565.60 |
| 2 |
G. Bortolotto and Company, Inc. |
$1,760,775.48 |
| 3 |
Bay Cities Paving & Grading, Inc. |
$1,844,328.85 |
| 4 |
C.F. Archibald Paving, Inc. |
$1,872,770.80 |
| 5 |
Granite Construction Co. |
$1,905,549.00 |
| 6 |
DeSilva Gates Construction |
$1,926,740.00 |
| 7 |
RGW Construction, Inc. |
$1,938,909.00 |
| 8 |
Top Grade Construction, Inc. |
$2,159,169.65 |
Project Name: Storm Damage Repairs Project
| Project No.: |
CIP 5417 |
| Date: |
June 25, 2008 - 2:00 PM |
| Project Manager: |
Robin Bartlett |
| |
(925) 973-2683 |
| ENGINEER'S ESTIMATE |
TOTAL BID |
| |
$2,634,529.00 |
| No. |
CONTRACTORS |
TOTAL BID |
| 1 |
Independent Construction |
$1,665,041.25 |
| 2 |
Odyssey Companies |
$2,042,344.45 |
| 3 |
HSR, Inc. |
$2,144,990.00 |
| 4 |
Fanfa, Inc. |
$2,311,164.50 |
| 5 |
Gordon N. Ball, Inc. |
$2,425,713.00 |