Plan Submittal
Guidelines
Re-submittals
Remember to always check with the
Planning Division at (925) 973-2560 to confirm zoning requirements prior to beginning your
project!

REQUIRED DOCUMENT SUBMITTAL
(Please provide three (3) complete sets)
-
Return three (3) sets of
revised plans, two (2) sets of supporting documentation, one (1) set of
originally submitted plans, an itemized written response and a
re-submittal request form.
-
Submit to the Permit
Specialist at the Building and Safety Services counter. He/she will ask
the Planning Division to review (note: under
most circumstances, Planning Division review can be performed
over-the-counter).
-
Permit Specialist date stamps
request form. He/she date
stamps "received" on all documentation, enters information
into computer and routes as required. Plans are routed and recheck
begins.
-
Turnaround time is one (1) to
five (5) business days.
|