Plan Submittal
Guidelines
Residential Solar Photovoltaic
Remember to always check with the
Planning Division at (925) 973-2560 to confirm zoning requirements prior to beginning your
project!
REQUIRED DOCUMENT SUBMITTAL
(Please submit three (3) complete sets)
- Plot Plan:
(indicate scale); lot
dimensions; plan view of the site showing the location of buildings
undergoing interior demolition; dimensions of buildings, building
setbacks and yards; north arrow; identification of all streets and
rights-of-way adjacent to the site; location of all driveways and site
entrances. Provide location of solar panels.
- Installation Details:
Provide
weight of panel, number of panels, area covered, listing of panel (UL),
and equipment listing. When roof mounted: provide type of existing roofing
materials, weight of existing roofing materials, attachment of panel
support to structure. When roofing material and sheathing exceed eight (8)
pounds per square foot provide structural calculations. When installed on
other structure provide details of structure (framing) and possibly
structural calculations.
|